Planning

Planning

CGE was selected by the City of Eufaula to develop a calibrated water model of the city’s water distribution system and then create a Capital Improvements Plan (CIP). The project began with an inventory of the existing system, including waterline sizes and lengths, elevated and ground storage...

Planning

Cowan Group Engineering assisted and worked with the City of Perkins staff in the study and hydraulic analysis of the entire water system. The system included 29.6 miles of waterlines, two (2) standpipes, one (1) elevated storage tank, three (3) water wells, and one booster station. The waterlines...

Planning

The City of Muskogee serves a population of approximately 39,000. In addition to serving the local residents, the City serves several water districts with a total population served of approximately 63,000 through over 2 million linear feet of water distribution lines.  The scope of services included...